# Engen-Led Consortium Details R40 Billion Integrated LNG-to-Power Project in Durban
- URL: https://www.africainvestorreview.com/engen-led-consortium-details-r40-billion-integrated-lng-to-power-project-in-durban/
- Published: 2026-11-23T22:55:00.000Z
- Updated: 2026-11-24T04:02:24.000Z
- Description: Engen, VTTI, Vitol, and ACWA advance plans for a 1.9 GW gas-to-power plant and LNG import terminal in KwaZulu-Natal, targeting operations in the second half of 2031.
- Author: Charles S.
- Tags: Macro & Markets, Southern Africa, Digital Economy

**DURBAN** — An [Engen](https://www.linkedin.com/company/engen/home/?ref=africainvestorreview.com)\-led consortium has reconfirmed plans to develop an integrated liquefied natural gas (LNG)-to-power project in Durban estimated at ZAR 40 billion (\~$2.3 billion).

The proposed infrastructure pairs an LNG import terminal and associated pipelines at the Port of Durban with a 1.9 GW combined cycle gas turbine (CCGT) power plant on the former Engen refinery site, which is being converted into a fuel import storage facility. Designed to generate power equivalent to roughly 3.9 million households alongside gas supply for KwaZulu-Natal industrial users, the project targets construction start in late 2028 and operations in the second half of 2031, subject to a final investment decision (FID), South Africa’s second Gas-to-Power procurement round, and regulatory and environmental approvals.

## Consortium Roles & Market Context

The project brings together specialized international partners and aims to address shifting regional gas dynamics:

- **Consortium Structure:** Engen leads the prospective consortium while targeting roughly 30% ownership by South African Broad-Based Black Economic Empowerment (B-BBEE) partners. VTTI will develop and operate the LNG terminal and pipelines, Vitol will supply LNG, and ACWA will develop the 1.9 GW power plant.
- **Regasification & Gas Supply:** The import terminal is planned with approximately 5 billion cubic metres per annum of peak regasification capacity to help South Africa manage an anticipated decline in pipeline gas imports from Mozambique as existing gas fields mature.
- **Industrial & Port Value:** Beyond power generation and industrial gas supply across KwaZulu-Natal, including potential support for energy-intensive assets such as data centres, preliminary estimates point to more than ZAR 245 million per year in throughput-related revenue for the Port of Durban and potential vessel LNG bunkering infrastructure.

## Timeline & Economic Impact

Economic impact estimates prepared by FTI Consulting (in 2024 prices, covering direct, indirect, and induced effects) highlight significant construction and operational contributions:

- **Construction Phase:** Scheduled to begin in late 2028 ahead of a targeted H2 2031 start of operations, supporting roughly 4,500 person-years of employment across South Africa (up to around 1,000 workers on site at peak) and an estimated ZAR 26 billion contribution to South African GDP.
- **Operations Phase:** Expected to support roughly 740 ongoing jobs during operations, including around 220 direct roles, and contribute approximately ZAR 1.8 billion per year to South African GDP.

## Executive Commentary

> "Reliable energy supply underpins economic growth. Engen is delighted to be part of a project which could deliver energy to industry and power 3.9 million households. We look forward to working with our partners and stakeholders to deliver energy solutions to South Africa."  
> — [**George Roberts**](https://www.linkedin.com/in/george-roberts-82109a68/?ref=africainvestorreview.com), Managing Director and CEO of Engen and EVP South for [Vivo Energy](https://www.linkedin.com/company/vivoenergy/home/?ref=africainvestorreview.com)

## Project Overview

- **Lead & Consortium Partners:** Engen (lead); VTTI (LNG terminal and pipeline development/operation); Vitol (LNG supply); ACWA (power plant development); targeted \~30% B-BBEE partner ownership
- **Estimated Project Cost:** \~ZAR 40 billion (\~$2.3 billion)
- **Key Assets & Capacity:** Port of Durban LNG import terminal (\~5 billion cubic metres per annum peak regasification capacity), associated pipelines, and 1.9 GW CCGT power plant at the Engen refinery site
- **Target Schedule:** Construction targeted for late 2028; operations targeted for H2 2031 (subject to FID, South Africa’s second Gas-to-Power procurement round, and approvals)
- **Focus Sectors:** LNG, Gas-to-Power, Energy Infrastructure, Port & Logistics, and Industrial Power

[Engen-led consortium details plans to develop integrated LNG-to-power project in Durban - Vitol.comAn Engen-led consortium today reconfirmed its plans to develop an integrated LNG-to-power project in Durban. The proposed project would generate enough electricity to supply the equivalent of approximately 3.9 million households, while also providing a reliable source of gas to industrial users across KwaZulu-Natal. The estimated ZAR 40 billion project would…![](https://storage.ghost.io/c/8a/90/8a905702-b441-4eb9-8a34-5fdeec861dd7/content/images/icon/favicon-32x32-1-71873bf2-1e0c-4568-81f6-ab18a54976a9.png)Vitol.comMatt Chatterton![](https://storage.ghost.io/c/8a/90/8a905702-b441-4eb9-8a34-5fdeec861dd7/content/images/thumbnail/7c3d78902a346a8daaac49e3ddd1337475c95c69a1654cd9cf08835e308893c6-63bfe8a6-e9c7-4b00-a809-e692b5441cfa.jpg)](https://www.vitol.com/engen-led-consortium-details-plans-to-develop-integrated-lng-to-power-project-in-durban/?ref=africainvestorreview.com)

---

### The Intelligence Engine for African Private Capital

Access complete transaction breakdowns, fund strategy updates, and market commentary directly on our platform.

[Become a member](#/portal/signup)