Engen-Led Consortium Details R40 Billion Integrated LNG-to-Power Project in Durban
Engen, VTTI, Vitol, and ACWA advance plans for a 1.9 GW gas-to-power plant and LNG import terminal in KwaZulu-Natal, targeting operations in the second half of 2031.
DURBAN — An Engen-led consortium has reconfirmed plans to develop an integrated liquefied natural gas (LNG)-to-power project in Durban estimated at ZAR 40 billion (~$2.3 billion).
The proposed infrastructure pairs an LNG import terminal and associated pipelines at the Port of Durban with a 1.9 GW combined cycle gas turbine (CCGT) power plant on the former Engen refinery site, which is being converted into a fuel import storage facility. Designed to generate power equivalent to roughly 3.9 million households alongside gas supply for KwaZulu-Natal industrial users, the project targets construction start in late 2028 and operations in the second half of 2031, subject to a final investment decision (FID), South Africa’s second Gas-to-Power procurement round, and regulatory and environmental approvals.
Consortium Roles & Market Context
The project brings together specialized international partners and aims to address shifting regional gas dynamics:
- Consortium Structure: Engen leads the prospective consortium while targeting roughly 30% ownership by South African Broad-Based Black Economic Empowerment (B-BBEE) partners. VTTI will develop and operate the LNG terminal and pipelines, Vitol will supply LNG, and ACWA will develop the 1.9 GW power plant.
- Regasification & Gas Supply: The import terminal is planned with approximately 5 billion cubic metres per annum of peak regasification capacity to help South Africa manage an anticipated decline in pipeline gas imports from Mozambique as existing gas fields mature.
- Industrial & Port Value: Beyond power generation and industrial gas supply across KwaZulu-Natal, including potential support for energy-intensive assets such as data centres, preliminary estimates point to more than ZAR 245 million per year in throughput-related revenue for the Port of Durban and potential vessel LNG bunkering infrastructure.
Timeline & Economic Impact
Economic impact estimates prepared by FTI Consulting (in 2024 prices, covering direct, indirect, and induced effects) highlight significant construction and operational contributions:
- Construction Phase: Scheduled to begin in late 2028 ahead of a targeted H2 2031 start of operations, supporting roughly 4,500 person-years of employment across South Africa (up to around 1,000 workers on site at peak) and an estimated ZAR 26 billion contribution to South African GDP.
- Operations Phase: Expected to support roughly 740 ongoing jobs during operations, including around 220 direct roles, and contribute approximately ZAR 1.8 billion per year to South African GDP.
Executive Commentary
"Reliable energy supply underpins economic growth. Engen is delighted to be part of a project which could deliver energy to industry and power 3.9 million households. We look forward to working with our partners and stakeholders to deliver energy solutions to South Africa."
— George Roberts, Managing Director and CEO of Engen and EVP South for Vivo Energy
Project Overview
- Lead & Consortium Partners: Engen (lead); VTTI (LNG terminal and pipeline development/operation); Vitol (LNG supply); ACWA (power plant development); targeted ~30% B-BBEE partner ownership
- Estimated Project Cost: ~ZAR 40 billion (~$2.3 billion)
- Key Assets & Capacity: Port of Durban LNG import terminal (~5 billion cubic metres per annum peak regasification capacity), associated pipelines, and 1.9 GW CCGT power plant at the Engen refinery site
- Target Schedule: Construction targeted for late 2028; operations targeted for H2 2031 (subject to FID, South Africa’s second Gas-to-Power procurement round, and approvals)
- Focus Sectors: LNG, Gas-to-Power, Energy Infrastructure, Port & Logistics, and Industrial Power

The Intelligence Engine for African Private Capital
Access complete transaction breakdowns, fund strategy updates, and market commentary directly on our platform.
Written by
Read next
Continental Considers Discontinuing Tire Production at Its Gqeberha Plant in South Africa
The German tyre maker initiates a Section 189A consultation putting roughly 950 jobs at risk, following prior Eastern Cape manufacturing exits.
AgTech Startup Crop Cura Launches Operations in Rwanda
Registered with the Rwanda Development Board, Crop Cura Rwanda Limited rolls out digital agronomy and field-mapping infrastructure to connect over 10,000 smallholder farmers with lenders and insurers.
Namibian Copper Producer Bezant Resources Secures £4M Debt Facility for Hope & Gorob Expansion
The AIM-listed mining firm secures non-convertible debt financing from US-based YA II PN Ltd as copper concentrate production begins at its Namibian asset ahead of a November 2026 maiden shipment.Axmed Secures $4.28 Million From the Gates Foundation to Expand Retail Pharmacy Procurement in Kenya and Nigeria
The healthcare procurement platform deploys $2.28 million to launch Axmed Retail for Kenyan pharmacies and $2 million for family planning procurement in Nigeria.
Continental Considers Discontinuing Tire Production at Its Gqeberha Plant in South Africa
The German tyre maker initiates a Section 189A consultation putting roughly 950 jobs at risk, following prior Eastern Cape manufacturing exits.
Cloud9 Acquires Canadian Money Services Business Monix Pay
The digital bank for African consumers and businesses gains a FINTRAC-registered Canadian subsidiary to connect cross-border commerce with fewer intermediaries.